Mumbai: Engineers India Limited Team achieves Mechanical Completion of New VPS Unit (VDU) at Mumbai Refinery Expansion Project (MREP), at HPCL Refinery, Mumbai. The execution of the brand new VPS unit was accomplished regardless of challenges on account of acute house constraints and present manholes / UG constructions inside & across the plot space.

Apart from that, the Plant space is encircled with different present items/amenities on operating situation and as such, correct entry to execute the work was solely from one aspect. The execution required six businesses to perform concurrently, which required minute planning & utmost care and security.

However, the location took rather a lot of security precautions & use progressive concepts to finish the works inside schedule. In spite of Mumbai being one of the main affected cities in COVID-19 Pandemic and its main implications on the mission since March 2020 i.e., restricted availability of manpower and adherence to security measures as per the federal government tips, younger & enthusiastic staff of EIL, HPCL & contractors put of their all out efforts for profitable mechanical completion of this unit.

Posted Date :  16-06-21

Related Posts